You said “YES!” Thank you!
Teacher and Staff Pay
Pay increase for all faculty and staff in the 2021-2022 school year.
Facility Upgrades
Project | Anticipated Start Date | Completion Date |
Bus Only Lane, Additional Turning Lane, and New ECC Entrance |
||
-Begin Excavating | May or June 2021 | August 2021 |
-Lay Asphalt | July 2021 | August 2021 |
-Project Completion | End of July 2021 | August 2021 |
Presentation System Install for ES | End of July 2021 | August 2021 |
ADA Lock Upgrades MS | ||
-Order | May 2021 | May 2021 |
-Install | June or July 2021 | August 2021 |
Vape Sensors | ||
-Order | End of April 2021 | April 30, 2021 |
-Install | May or June 2021 | October 2021 |
Cafeteria Tables ES | ||
-Order | End of April 2021 | April 30, 2021 |
-Install | July 2021 | August 2021 |
Training Facility | ||
-Break Ground | End of May 2021 | July 2021 |
-Rough-in | June 2021 | October 2021 |
-Dried | July or August 2021 | November 2021 |
-Work Completion | September or October 2021 | March 2022 |
Middle School Remodel | ||
-Demolition | June 2021 | July 2021 |
-Rough-in | July or August 2021 | July 2021 |
-Work Completion | August or September 2021 | February 2022 |
Elementary Pods | ||
-Demolition | June 2021 | July 2021 |
-Install flooring, shades, and furniture | July 2021 | Flooring & furniture complete August 2021, shades complete November 2021 |
-Work Completion | August 2021 | August 2021 |